What is a Commissioning Checklist?
A commissioning checklist is used to easily perform comprehensive installation, functional, and operational inspections of a project equipment, system, or components. This checklist helps resolve any detected failures and ensure full functionality of project assets.
At What Point Does Pre-commissioning End and Commissioning Begin?
There are regional differences when it comes to common parlance in pre-commissioning and commissioning. Pre-commissioning is sometimes referred to as Cold Commissioning, Static Commissioning, or Mechanical Completion; on the other hand, commissioning is sometimes referred to as Hot Commissioning, Live/Dynamic Commissioning, or Start-up. Therefore, commissioning teams experience difficulty in determining the proper procedure. Here is a run-down of what needs to be done during pre-commissioning and commissioning, respectively:
Pre-commissioning Procedure
- Piping and Instrumentation Diagram (P&ID) Check, also known as System Check or Walkdown, should be performed by the commissioning team to identify engineering and construction errors. Create a P&ID Punch List and address identified issues before pre-commissioning.
- Pre-commissioning activities start from mechanical completion, where running-in of equipment such as control system sequence tests (Dry Commissioning), water or solvent introduction to closed-loop pumps (Wet Commissioning), and other operating scenarios where process fluids are NOT YET used.
The Defining Point: Pre-Startup Safety Review (PSSR)
PSSR is a thorough safety inspection of a new or modified facility to be conducted before commissioning. This is the point where pre-commissioning ends and commissioning begins. Correct any system failure, resolve all safety risks, and re-take the PSSR to comply with health and safety regulations prior to commissioning.
Commissioning Procedure
- Commissioning is the overall performance testing of the facility and its systems such as HVAC, pumps, piping, and lighting. Outstanding punch points should be resolved before routine operation. During a manufacturing plant commissioning, process conditions are established and process fluids (the actual raw materials to be used for routine production) are introduced into the system.
- Initial Operation, or the first production run, aims to determine if the production process manufactures output that meets design requirements. Easily identify non-conformance and adjust the system or optimize the process by performing a first article inspection prior to routine production.
What is Included in a Commissioning Checklist
A commissioning checklist is an essential tool used in various industries to ensure that systems, equipment, and processes are installed and functioning as intended. The contents of a commissioning checklist can vary based on the project type and assets involved, but typically include several key elements:
- Pre-Installation Checks: Verify design, equipment, and site conditions.
- Installation Verification: Ensure proper installation and secure connections.
- System Testing: Test functionality, safety systems, and performance.
- Adjustments and Calibration (TAB): Balance and calibrate systems for optimal performance.
- Documentation and Compliance: Ensure proper documentation and regulatory compliance.
- Training and Handover: Train staff and provide operational resources.
- Post-Commissioning Follow-Up: Address any outstanding issues and schedule follow-ups.
FAQs About Commissioning
What are the steps in commissioning?
What is a commissioning inspection?
What should be included in a commissioning checklist?
