Use this inspection and test plan to manage construction of an internal pump plinth for a booster pump station. Steps cover setout to IFC drawings, clean formwork, N12 reinforcement at 150 mm centres tied to starters, ordering N40 concrete, slump and quantity checks, pumping and added water records. Includes a pre-pour hold point inspection by STP Consultants, pour and vibration, strip and clean, completion of the concrete pour record sheet, and photo capture of concrete dockets. Final ITP sign off by Fergus Builders and STP Consultants.
With SafetyCulture you can
With SafetyCulture you can
About author
This community page makes available free workplace checklists and templates created by other users within the SafetyCulture community. SafetyCulture has re-published this content and where possible, has credited the original author. SafetyCulture has not verified the accuracy, reliability or suitability of any community content. You agree that your use of any of this content is in accordance with SafetyCulture’s Terms and Conditions.