This step by step standard work instruction guides a planned monthly offline visual inspection of underground 4590 portal air compressors. It covers pre start preparations, isolation and lock out tag out, daily checks such as leaks, hose wear, filters, fasteners, coolant and drain valve. You will record pressure, capacity, running hours and temperature, respond to controller warnings by replacing filters and separator, and complete cleanup and handover to the supervisor, with defects and improvements noted.
With SafetyCulture you can
With SafetyCulture you can
About author
This community page makes available free workplace checklists and templates created by other users within the SafetyCulture community. SafetyCulture has re-published this content and where possible, has credited the original author. SafetyCulture has not verified the accuracy, reliability or suitability of any community content. You agree that your use of any of this content is in accordance with SafetyCulture’s Terms and Conditions.